Home  Background  Products  News  Archives  Contact Us

AWARDS:
Siemens TIA User Forum on the 24-26 October 2005 – Ram-Tec Systems has been awarded with best PLC Project for their Sebokeng Water solution.

REFERENCES:
Certificates – Please see Products / Services page.

SCAW METALS – August 2003

CLIENT:
Fuchs System Technik
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R1 Million  
COMPLETION:
Commissioning is scheduled for the beginning of November 2003
DESCRIPTION:
The contract involves SCADA process control, CAD drawings, PLC and SCADA equipment being installed includes Telemecanique & Wonderware InTouch. 
LOCATION:
Germiston
CONTACT:
Ram-Tec Systems - Andries Bolleurs

NESTLE WATERS – July 2003
CLIENT:
Solutions Technology
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R2 Million
COMPLETION:
Commissioning is scheduled for the end of July 2003
DESCRIPTION:
The contract involves Electrical, Installation & SCADA process control.PLC and SCADA equipment being installed includes Telemecanique & Wonderware InTouch.
LOCATION:
Olifantsfontein
CONTACT:
Ram-Tec Systems - Ian Tumiel

SOUTH AFRICAN BREWERIES plc – October 2002 – Brewhouse Upgrade
CLIENT:
SAB Chamdor
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R2.5 Million
COMPLETION:
The plant must be commissioned by the end of January 2003
DESCRIPTION:
The contract involves standardizing the E& I plant in the Brewhouse; and optimising the PLC I/O design to fully automate the brewhouse.PLC and SCADA equipment being installed includes Modicon Quantum with Wonderware InTouch.
LOCATION:
The Brewhouse is located in Krugersdorp
CONTACT:
Ram-Tec Systems - Anton Stassen

YORK INTERNATIONAL – September 2002 - Underground Refrigeration Plant PLC Systems
CLIENT:
York MiacInternational
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R1 Million
COMPLETION:
The plant must be commissioned by the end of November 2002
DESCRIPTION:
The plant will be controlled by Modicon Compact with Magelis HMI.
LOCATION:
Krugersdorp
CONTACT:
Ram-Tec Systems - Ian Tumiel

GWK LIMITED – September 2002 - GWK Upgrade
CLIENT:
GWK
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R1 Million
COMPLETION:
The plant must be commissioned by the end of October 2002
DESCRIPTION:
The contract is for the Turnkey Electrical, Control & Instrumentation of the Silo at Prieska.
LOCATION:
Prieska
CONTACT:
Ram-Tec Systems - Ian Tumiel

Nestle – July 2002 - Niro 1 Babelegi
CLIENT:
Nestle
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R1.5 Million
COMPLETION:
The plant must be commissioned by the end of April 2003
DESCRIPTION:
The contract is for the Turnkey automation, control and electrical systems for the Niro 1 Tower.The plant produces milk powder products such as coffee creamers.
LOCATION:
Babelegi in Hammanskraal
CONTACT:
Ram-Tec Systems - Ian Tumiel

Pioneer – March 2002 - Pioneer Phase 2 Dryer
CLIENT:
Pioneer Seeds
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R2.5 Million
COMPLETION:
The plant must be commissioned by the end of November 2002
DESCRIPTION:
The contract is for the Turnkey electrical, control system & instrumentation for the new sorting, dryer and shelling plants.The plant will be controlled by both Modicon Quantum and Momentum PLC's.
LOCATION:
Rosslyn in Pretoria
CONTACT:
Ram-Tec Systems - Ian Tumiel

SOUTH AFRICAN BREWERIES plc – January 2002- Brewhouse Batch Implementation
CLIENT:
SAB Chamdor.
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
Unstated
COMPLETION:
The project must be completed by August 2002.
DESCRIPTION:
A Batch control engine is to be implemented in the Chamdor Brewhouse during 2002. The scope of this project is : (1) to standardize the E&I plant in the Brewhouse, (2) to complete all related documentation, (3) and to do the IO design for optimizing the PLC usage, (4) to do the design and pricing for extra instrumentation/devices required to fully automate the brewhouse.
LOCATION:
The Brewhouse is located in Krugersdorp
CONTACT:
SAB Chamdor: Rudolf Van Wyk (011) 951-2600 Ram-Tec Systems: Ian Tumiel

NESTLE – November 2001 - Coffee Creamer Production Plant
CLIENT:
Nestle South Africa (Pty) Ltd.
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
Approximately R1.5 Million.
COMPLETION:
The project must be completed by the end of April 2002.
DESCRIPTION:
World class automation and control systems are being installed using the latest PLC and SCADA technology. Ram-Tec will also carry out the associated turnkey electrical and instrumentation upgrade for the plant.
LOCATION:
The plant is located in Babelegi near Pretoria
CONTACT:
Ram-Tec Systems: Ian Tumiel

TECHMACH TECHNOLOGY – November 2001 - Maize Grading and Sorting Plant
CLIENT:
Techmach Technology
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
Approximately R1.5 Million
COMPLETION:
The project must be completed by the end of December 2001.
DESCRIPTION:
World class automation and control systems are being installed using the latest PLC and SCADA technology. Ram-Tec will also carry out the associated turnkey electrical and instrumentation upgrade for the plant.
LOCATION:
The plant is situated in Rosslyn near Pretoria
CONTACT:
Ram-Tec Systems: Ian Tumiel

BIOTECHNOLOGY PRODUCT MANUFACTURING – October 2001
CLIENT:
Seravac Manufacturing (pty) Ltd
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
Approximately R2 Million.
COMPLETION:
The upgrade must be completed by the end of January 2002.
DESCRIPTION:
New world class automation and control systems are being installed using the latest PLC and SCADA technology. Ram-Tec will also carry out the associated turnkey electrical and instrumentation upgrade for the plant.
LOCATION:
The Seravac Plant is situated in Epping Cape Town.
CONTACT:
Ram-Tec Systems: Ian Tumiel

RAND WATER – September 2001 - Mapleton Pumping Station Disinfection Facilities
CLIENT:
Rand Water
CONTRACTOR:
Klomac will design and build the complete plant as specified. Black Empowerment Company Mathosi Engineering Services (MES) is the Electrical Consultant. Ram-Tec Systems for the Control and Electrical
EST. VALUE:
Total Project R4 Million - The Electrical and Control portion is approximately R1Million.
COMPLETION:
The system must be commissioned by the end of January 2002.
DESCRIPTION:
The contract is to supply and install Chlorine and Ammonia Dosing facilities at Mapleton Pump Station. The dosing will be controlled by a PLC and SCADA control system.
LOCATION:
The Pump Station is 40Km South East of Johannesburg
CONTACT:
Klomac: Colin Beyers (012) 710-3100 - MES: Daniel Mathosi 082 331 6188 - Ram-Tec Systems: Ian Tumiel

SOLUTIONS TECHNOLOGIES – October 2000 - Goodhope UHT Project
CLIENT:
Good Hope Food Beverage Holdings
CONTRACTOR:
Main Contractor - Solution Technologies - Ram-Tec Systems
EST. VALUE:
Total Project R50 Million - Ram-Tec's Contract +- R2 Million
COMPLETION:
The plant must be commissioned by the end January 2001.
DESCRIPTION:
The contract is for the turnkey electrical, control & instrumentation system for the plant & includes Project Management , Engineering, PLCs', SCADA, Batching, Control Panels & installation.
LOCATION:
Montagu, Cape Town.
CONTACT:
Ram-Tec Systems - Ian Tumiel

WEIR ENVIG– August 2000- Ion Exchange Demineralisation Plant Control System
CLIENT:
Sasol Secunda - Weir Envig is the main contractor for the water treatment plant
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
Not Stated
COMPLETION:
The plant must be commissioned by the end of October 2000.
DESCRIPTION:
The contract is for the turnkey control system for the plant and includes a PLC, SCADA, Engineering and Control Panels
LOCATION:
Secunda
CONTACT:
Ram-Tec Systems - Ian Tumiel

USF CHEMATRON – May 2000- Demin, Drinking & Process Water Electrical, Instrumentation & Control System
CLIENT:
Iscor Newcastle - USF Rossmark of Holland Main Contractor - USF Chematron Local Subsidiary
CONTRACTOR:
Ram-Tec Systems
EST. VALUE:
R2 Million Plus
COMPLETION:
The plant must be commissioned by the end of August 2000
DESCRIPTION:
The contract is for the turnkey electrical, control system & instrumentation for the plant.The plant will be controlled by Modicon Quantum PLC's & SCADA. MCC/PLC control panels and instrumentation will be supplied.
LOCATION:
Newcastle
CONTACT:
Ram-Tec Systems - Ian Tumiel

REFERENCE LIST OF WORK COMPLETED

Client
Description
Approximate Value
Vametco Mineral Corp. Fully Automated Evaporator/Crystallizer R 500 000
Chematron-Vivendi Water
ABC Wadeville
Iscor Newcastle

Water Treatment Plant
Demin Plant

R 250 000
R2 500 000
DB Thermal
Iscor Vereeniging
Rand Water Zuikerbosch

Water Treatment Plant
Recoverd Wash Water Treatment Plant

R 800 000
R2 500 000
HL & H Mining Timber Pole Sorting Systems Numerous R2 000 000
ERWAT Olifantsfontein Water Treatment Works Phase III. R1 500 000
Fedmis-Phalaborwa Filler Plant upgrade R. 750 000
Greater Metro Council Driefontein Waste Water Treatment Plant R 650 000
Good Hope Beverages Juice Extraction Plant. R2 500 000
IMS PPColumbus Stainless Effluent & Evaporator Plant R1 500 000
Lekoa Company Sebokeng Waste Water Treatment Plant R2 500 000
LTA - Sasko Escourt Mill & Packaging Plant Upgrade R2 500 000
Shenhua Mine - China Rapid Load -out Station PLC & SCADA R2 000 000
Pioneer Seeds New sorting, dryer and shelling plants R2 500 000
SAB Chamdor Brewhouse Upgrades R3 000 000
Iscor
Sishen Mine
Grootegeluk Mine

A sized Load Out Stations
Waste Disposal System

R1 500 000
R 500 000
Seravac Laboratory Biotechnology Plant Automation. R2 500 000
SFW Canning Line Springs R 400 000
Suidwes Coop Makwassie Peanut Sorting Plant R 400 000
Tiger Oats
Cereal & Malt
S.A Oil Mills

Barley Pasteurization Automation
Peanut Roasting Plant

R1 000 000
R 400 000
Weir-Envig
Bayside Aluminium-
Sasol Secunda

DAF Water Treatment Plant
Demin Plant

R 500 000
R1 000 000